Onsdag 30 April | 11:44:56 Europe / Stockholm

Kalender

Est. tid*
2025-11-26 08:00 Kvartalsrapport 2025-Q3
2025-08-27 08:00 Kvartalsrapport 2025-Q2
2025-05-30 N/A X-dag ordinarie utdelning EWIND 0.00 NOK
2025-05-28 N/A Årsstämma
2025-05-21 08:00 Kvartalsrapport 2025-Q1
2025-02-26 - Bokslutskommuniké 2024
2024-11-19 - Kvartalsrapport 2024-Q3
2024-08-28 - Kvartalsrapport 2024-Q2
2024-05-30 - X-dag ordinarie utdelning EWIND 0.00 NOK
2024-05-29 - Årsstämma
2024-05-22 - Kvartalsrapport 2024-Q1
2024-02-29 - Bokslutskommuniké 2023
2023-11-14 - Kvartalsrapport 2023-Q3
2023-08-17 - Kvartalsrapport 2023-Q2
2023-05-26 - X-dag ordinarie utdelning EWIND 0.00 NOK
2023-05-25 - Årsstämma
2023-05-12 - Kvartalsrapport 2023-Q1
2023-03-24 - Extra Bolagsstämma 2023
2023-02-24 - Bokslutskommuniké 2022
2022-11-15 - Kvartalsrapport 2022-Q3
2022-08-17 - Kvartalsrapport 2022-Q2
2022-05-09 - X-dag ordinarie utdelning EWIND 0.00 NOK
2022-05-06 - Årsstämma
2022-05-03 - Kvartalsrapport 2022-Q1
2022-02-15 - Bokslutskommuniké 2021

Beskrivning

LandNorge
ListaOslo Bors
SektorTjänster
IndustriShipping & Offshore
Edda Wind är ett norskt bolag verksamma inom vindkraftsindustrin. Bolaget tillhandahåller servicefartyg och service till den globala vindkraftsindustrin till havs, där Edda Winds fartyg åker ut med tekniker för att erbjuda service till vindkraftverken. Störst verksamhet återfinns inom Europa. Edda Wind grundades år 2015 och har sitt huvudkontor i Norge.
2024-02-29 07:00:00
Haugesund, 29 February 2024: Edda Wind's operations have been progressively
expanding, with six vessels operational by the end of Q4 2023. The group
delivered consolidated revenue of EUR 11.4m, representing 55% growth vs. Q4
2022. EBITDA was negatively impacted by frontrunner cost and offhire implying
that consolidated EBITDA came in at negative EUR 1.1m.

Selected key developments in Q4 2023 and after balance sheet date:

- Revenue of EUR 11.4m (+55% growth vs. Q4-22)
- EBITDA of EUR -1.1m, negatively impacted by frontrunner cost (approx. EUR
3.5m) and offhire (approx. EUR 3m)
- Edda Nordri commenced operation in December 2023
- Attractive EUR 161m green term loan facility secured in December 2023
Post Q4 2023 events:
- Sales and Purchase Agreement (SPA) entered into for the sale of Edda Passat
- Seatrials commenced for Edda Goelo
- System upgrades on gangways causing offhire

With a fleet to count thirteen vessels, excluding Passat but including vessels
under construction, Edda Wind is the leading C/SOV-operator in the market. Edda
Wind is experiencing a favorable demand outlook for C/SOV despite announced
delays and setbacks within the supply chain. Edda Wind also notes that delays
and unscheduled work at the wind farms result in additional work for CSOVs.

There is a limited amount of available vessels, including vessels under
construction in the coming years, and vessel demand is estimated to
significantly outgrow supply. The contract backlog was EUR 416m at the end of
the quarter. This, combined with several newbuilds uncommitted and able to
secure work in a market with great demand for this type of vessels, positions
Edda Wind to capitalise on the expected growth in the quarters and years to
come.

Presentation of the results:

Kenneth Walland (CEO) and Tom Johan Austrheim (CFO) will present the Q4 2023
results in a webcast at 08:30 CET today, 29 February 2024.

The presentation will be held in English and will be virtual. The presentation
can be followed through a live webcast from our website www.eddawind.com, or
https://channel.royalcast.com/hegnarmedia/#!/hegnarmedia/20240229_7

ABOUT EDDA WIND

Edda Wind is a leading offshore wind service company headquartered in Haugesund,
Norway. The Company develops, builds, owns and operates purpose-built Service
Operation Vessels ("SOV") and Commissioning Service Operation Vessels ("CSOV")
for offshore wind farms worldwide.

Edda Wind is creating the next generation offshore wind service vessels and
works closely with partners to develop new technologies to reduce emissions
without compromising operational capabilities or cost competitiveness.

The Company owns and operates three purpose-built offshore wind SOVs and three
CSOVs and eight nine dedicated offshore wind vessels under construction - one
SOV and seven CSOVs. All newbuild vessels are prepared for zero-emission
utilising liquid organic hydrogen carrier and/or methanol as an energy source.

Read more: www.eddawind.com

For further information, please contact:
Lars Stubhaug, VP Finance Edda Wind
Phone: +47 917 42 725
E-mail: lars.stubhaug@eddawind.com

Tom Johan Austrheim, CFO Edda Wind
Phone: +47 982 09 873
E-mail: tom.johan.austrheim@eddawind.com